25-003 Marymede CC Stage 5 - Offentlig byggarbetsplats
-
29th juni 2026, MOnday 29-06-2026
Planned Activities
Formworkers will complete the formwork for the Level 2 deck.
Steel fixers will commence the bottom steel to the formwork deck.
Plumbers will start the stormwater line on the live road. A separate toolbox talk must be completed and signed by all workers prior to commencing these works.
Concretors will continue installing formwork to the amphitheatre.
Electricians are working on installing power to the woodwork equipment in the Stage 4 high-risk areas.
Important Notes
All crews are to follow site-specific safe work procedures and supervision requirements.
The stormwater works on the live road are to remain controlled under the separate toolbox and sign-on process.
All personnel must be aware of adjacent work fronts and maintain clear communication throughout the day.
High-risk areas are to be managed in accordance with the site safety plan and access restrictions.
Site Coordination
Ensure:
Work areas are clearly separated where required.
Plant, materials, and pedestrian movements are managed safely.
Any changes to the sequence of works are communicated to all affected crews.
All workers sign on to the relevant pre-starts before starting.
Cleaner version for posting
Today’s Site Activities
Formworkers: Complete Level 2 deck formwork.
Steel fixers: Start bottom steel to formwork deck.
Plumbers: Commence stormwater line works on live road. Separate toolbox talk and sign-off required before starting.
Concretors: Continue formwork installation to amphitheatre.
Electricians: Install power to woodwork equipment in Stage 4 high-risk areas. -
26th juni 2026, Friday tool box
Toolbox Talk: Working Safely on Site
Today’s focus is on working safely at heights, wearing the correct PPE, testing and tagging tools, keeping our work areas clean, and parking safely off site. These are simple controls, but they prevent injuries, damage, delays, and complaints. Working at height is a high-risk activity, and Safe Work Australia says risks must be eliminated or minimised so far as is reasonably practicable, with proper controls in place.
1. Working at heights
Any work where there is a risk of falling must be planned and controlled before we start. Use the correct fall protection, follow the SWMS, and do not take shortcuts such as standing on unsafe surfaces or using equipment incorrectly. Keep platforms, ladders, access ways, and work areas clear so no one is exposed to a fall hazard.
2. PPE
Wear the required PPE at all times: helmet, hi-vis, safety boots, gloves, eye protection, and any task-specific protection needed for the job. PPE is the last line of defence, so it must be worn correctly and kept in good condition. If your PPE is damaged, missing, or not suitable, report it before starting work.
3. Test and tag tools
All electrical tools must be tested and tagged before use, and any damaged leads, plugs, or tools must be removed from service immediately. Never use untested or suspect equipment, and never bypass safety devices. If a tool looks unsafe, stop using it and report it straight away.
4. Housekeeping
Everyone is responsible for cleaning up after themselves. Put tools away, remove waste, keep walkways clear, and do not leave materials or offcuts in access areas. Good housekeeping reduces slips, trips, falls, and lost time.
5. Lunch room
The lunch room must be left clean and tidy after use. Put rubbish in the bins, wipe down tables, and leave the area ready for the next crew. A clean lunch room is part of site discipline and shows respect for everyone on site.
6. Parking
There is no parking on site, so all vehicles must be parked on Cooks Road or in the approved off-site parking area. Do not block driveways, access points, neighbours’ property, or traffic routes. Good parking control helps keep the site safe, legal, and professional.
Closing message
Safety is everyone’s responsibility. If you see a fall risk, unsafe tool, poor housekeeping, or a parking issue, stop and report it before it becomes an incident. Let’s work safely, keep the site tidy, and look after each other. -
22nd mars 2023, WorkSafe EWP Standard - November 2022
EWP SWMS to be revised to include:
* EWP familiarity training for different types and models of EWPs.
* Safety Observers to be licensed or ticketed, safety observers to warn the operator(s) of hazards and ensure prompt rescue, need to have line of sight to the EWP operator(s), not to leave the work area until the EWP is lowered to a stowed position and the operator has alighted from the platform
Nuvarande väder på platsen
Senast uppdaterad den: 12:21
Temperatur: 15°C (App 13°C)
Vindhastighet: 4KMH
Max. vind: 7KMH @11:21
Regn sedan klockan 9 på morgonen: 0,2mm
Min temp: 1°C @07:44
Max temp: 15°C @12:20
Vindstöt: 13KMH
Max Gust: 13KMH @12:21
Observationsplats - Viewbank, VICTORIA
Tidszon - östaustralisk normaltid
Prognos - lördag, 1 augusti
Sunny.
Min: 7°C Max: 16°C
Risk för regn: 20%
Prognosplats - Watsonia, VICTORIA
Tidszon - östaustralisk normaltid
Imorgon - söndag, 2 augusti
Showers.
Min: 7°C Max: 14°C
Risk för regn: 90%
Förväntad nederbörd: 1 till 5mm
-
HammerTech - Getting Started With HammerTech Tier 3 Companies
Uppladdad 2024-10-24
save_alt Ladda ner -
Welcome Email Attachment - Safe Work Australia Safe Work Method Statement for High Risk Construction Work
Uppladdad 2020-03-24
save_alt Ladda ner -
Welcome Email Attachment - WorkSafe Safe work method statements-2018-11
Uppladdad 2020-03-24
save_alt Ladda ner
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.